- Report Date
- August 2013
Achievements in Last Period
- Acceptance review
- Increase memory on TEST which resolved performance issues
- Open JIRAs resolved
Issues
- Issue with Deployment Plan prevented deployment as scheduled on 27/08/13
Next Steps
- Preparation for LIVE deployment on 01/10/13
- Approved budget
- 35.0 days
- Activity this month
- 2.0 days
- Activity this year
- 2.0 days
- Activity to date
- 29.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days