Report for September 2013

Report Date
September 2013

 

Achievements in Last Period

  • No achievements this period

Issues

  • Planned deployment canceled due to fire at KB.  
  • Due to an issue with the LIVE service DR in the aftermath of the above, a new deployment date cannot be set until the LIVE service is fully restored. This work is scheduled for October. 

Next Steps

  • Agree new deployment date with Production and deploy. 

 

Project status set to Amber as no new deployment date is scheduled. 

Project Status
RAG Status
Time
RED
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014