Report for October 2013

Report Date
October 2013

Achievements in Last Period

  • No activity this month, two issues below are preventing deployment

Issues

  • Deployment has been hampered by remedial work after the fire at KB, where one of the LIVE servers will be rebuilt.
  • Investigation to be completed to ensure that these changes will not impact on the Polopoly Upgrade planned for later this year

 

Next Steps for November

  • Deploy solution to LIVE
  • Project remains Amber due to no deployment milestone set due to issues noted above.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
35.0 days
Activity this month
0.4 days
Activity this year
5.4 days
Activity to date
32.7 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014