Report for December 2013

Report Date
December 2013

Achievements in Last Period

  • Solution deployed to LIVE
  • Deployment review achieved

Issues

  •   No issues to report

Next Steps for October

  • Project will move to closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
35.0 days
Activity this month
2.7 days
Activity this year
10.5 days
Activity to date
37.9 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014