Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
Planning completed
Issues
Planning delayed due to impact of other UWS projects and resource availability due to illness.
Next Steps
The project will now be suspended until Mid-December. The next activity will be R&D work undertaken in January by Development Team.
Milestones
Target date | Title |
---|---|
05-Oct-2012 | Planning Review |
20-Jan-2013 | Analysis Sign Off |
- Approved budget
- 23.0 days
- Activity this month
- 1.1 days
- Activity this year
- 2.6 days
- Activity to date
- 3.1 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days