Report for September 2012

Report Date
September 2012

Achievements in Last Period

Planning completed

Issues

Planning delayed due to impact of other UWS projects and resource availability due to illness.

Next Steps

The project will now be suspended until Mid-December. The next activity will be R&D work undertaken in January by Development Team.

Milestones

Target dateTitle
05-Oct-2012Planning Review
20-Jan-2013Analysis Sign Off

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
1.1 days
Activity this year
2.6 days
Activity to date
3.1 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014