November 2012
- Report Date
- November 2012
Achievements in Last Period
- No activity, this project has been suspended until mid-December, the R&D will be completed in January 2013.
Issues
- No issues to report at this stage
Next Steps
- Project will start become active mid-December
Milestones
Target date | Title |
---|---|
21-Jan-2013 | Analysis Sign Off |
- Approved budget
- 24.0 days
- Activity this month
- 0.1 days
- Activity this year
- 2.8 days
- Activity to date
- 3.2 days
- Estimate to complete current year
- 20.8 days
- Estimate to complete future years
- 0.0 days