Report for January 2013

Report Date
January 2013

 

Achievements in Last Period

This project was reactivated in December

Issues

Due to other work with UWS003 and Drupal, this work has slipped by to 22/02/13

Next Steps

R&D work will complete

Milestones

Target dateTitle
05-Oct-2012Planning Review
22-Feb-2013Analysis Review

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
24.0 days
Activity this month
3.7 days
Activity this year
6.5 days
Activity to date
6.9 days
Estimate to complete current year
17.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014

Documentation