February 2013
- Report Date
- February 2013
Achievements in Last Period
- R&D and Analysis Review complete
- R&D has produced a new improved search tab
Issues
- Additional milestones will be dependent on resource availability
Next Steps
- Remaining milestones to be confirmed
- Some additional R&D to be completed
- Move new search tab on to DEV and TEST for UWP testing
Milestones
New milestone to be agreed and added next month.
- Approved budget
- 24.0 days
- Activity this month
- 4.3 days
- Activity this year
- 10.9 days
- Activity to date
- 11.3 days
- Estimate to complete current year
- 12.6 days
- Estimate to complete future years
- 0.0 days