Report for March 2013
- Report Date
- March 2013
Achievements in Last Period
- New milestones agreed for remaining work
- Build Review achieved
Issues
- No issues to report
Next Steps
- Conduct integration testing and sign off milestone
- Start UAT
Milestones
Target date | Title |
---|---|
29-Mar-2013 | Build Review |
05-Apr-2013 | Integration Review |
07-Jun-2013 | Acceptance Review |
18-Jun-2013 | Delivery |
28-Jun-2013 | Deployment Review |
12-Jul-2013 | Closure |
- Approved budget
- 35.0 days
- Activity this month
- 8.2 days
- Activity this year
- 19.1 days
- Activity to date
- 19.5 days
- Estimate to complete current year
- 15.4 days
- Estimate to complete future years
- 0.0 days