Report for March 2013

Report Date
March 2013

Achievements in Last Period

  • New milestones agreed for remaining work
  • Build Review achieved

Issues

  • No issues to report 

Next Steps

  • Conduct integration testing and sign off milestone
  • Start UAT

Milestones

Target dateTitle
29-Mar-2013Build Review
05-Apr-2013Integration Review
07-Jun-2013Acceptance Review
18-Jun-2013Delivery
28-Jun-2013Deployment Review
12-Jul-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
35.0 days
Activity this month
8.2 days
Activity this year
19.1 days
Activity to date
19.5 days
Estimate to complete current year
15.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Search Improvements (within Polopoly)
Code
UWS004
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
09-Jan-2014

Documentation