- Report Date
- April 2013
Achievements in Last Period
- Integration testing completed and milestone sign off achieved
Issues
- Performance concerns prevented initial Integration sign off these were partially resolved but his could become an issue during UAT
Next Steps
- UAT will be started by UWP, depending on programme priorities, rework may be delayed.
- Approved budget
- 35.0 days
- Activity this month
- 4.3 days
- Activity this year
- 24.4 days
- Activity to date
- 24.8 days
- Estimate to complete current year
- 12.5 days
- Estimate to complete future years
- 0.0 days