Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
Planning on-going
Issues
Planning delayed due to impact of other UWS projects, resource availability due to illness and planned annual leave.
Next Steps
Planning to be completed and Business Analysis to commence.
Milestones
Target date | Title |
---|---|
05-Oct-2012 | Planning Review |
30-Nov-2012 | Business Analysis Review |
16-Jan-2013 | Business Case Review |
31-Jan-2013 | Closure |
- Approved budget
- 122.0 days
- Activity this month
- 1.1 days
- Activity this year
- 2.6 days
- Activity to date
- 3.1 days
- Estimate to complete current year
- 119.0 days
- Estimate to complete future years
- 0.0 days