Report for September 2012

Report Date
September 2012

Achievements in Last Period

Planning on-going

Issues

Planning delayed due to impact of other UWS projects, resource availability due to illness and planned annual leave.

Next Steps

Planning to be completed and Business Analysis to commence.

Milestones

Target dateTitle
05-Oct-2012Planning Review
30-Nov-2012Business Analysis Review
16-Jan-2013Business Case Review
31-Jan-2013Closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
122.0 days
Activity this month
1.1 days
Activity this year
2.6 days
Activity to date
3.1 days
Estimate to complete current year
119.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Alternative Search Engine Investigation
Code
UWS005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Craig Middlemass
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-May-2013