Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • Planning completed.
  • Business Analysis has started with
  1. Contact to various vendors - this will feed into a matrix of Search Providers and their offerings.
  2. Contact made with targeted business units (Data source owners), meetings are scheduled for mid-November.
  3. Creating an IA and Content Strategy engagement document.

Issues

  • There are currently no issues to note

Next Steps

  • Business Analysis to be completed and signed off
  • A survey for Web Publishers Community will be prepared.
  • Interim Paper to be drafted for the Website Governance Group

Milestones

Target dateTitle
30-Nov-2012Business Analysis Review
16-Jan-2013Business Case Review
31-Jan-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
88.5 days
Activity this month
6.7 days
Activity this year
9.3 days
Activity to date
9.8 days
Estimate to complete current year
67.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Alternative Search Engine Investigation
Code
UWS005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Craig Middlemass
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-May-2013