Report for November
- Report Date
- November 2012
Achievements in Last Period
- Draft of recommendation based on Business Analysis Prepared (IA and Content Strategy engagement document)
- Interim Paper to be drafted for the Website Governance Group
- Review meeting held with Data Source Owners and analysis documented
Issues
- Some conflicts for UWS time with Drupal proof of concept project
Next Steps
- Business Analysis to be completed and signed off
- A survey for Web Publishers Community will be prepared.
- Dev Team and Dev Tech to complete their research and feed into IA and Content Strategy engagement document
Milestones
Target date | Title |
---|---|
07-Dec-2012 | Business Analysis Review |
16-Jan-2013 | Business Case Review |
31-Jan-2013 | Closure |
- Approved budget
- 88.5 days
- Activity this month
- 6.2 days
- Activity this year
- 15.5 days
- Activity to date
- 16.0 days
- Estimate to complete current year
- 61.7 days
- Estimate to complete future years
- 0.0 days