Achievements in Last Period

  • Draft of recommendation based on Business Analysis Prepared (IA and Content Strategy engagement document)
  • Interim Paper to be drafted for the Website Governance Group
  • Review meeting held with Data Source Owners and analysis documented

Issues

  • Some conflicts for UWS time with Drupal proof of concept project

Next Steps

  • Business Analysis to be completed and signed off
  • A survey for Web Publishers Community will be prepared.
  • Dev Team and Dev Tech to complete their research and feed into IA and Content Strategy engagement document

Milestones

 

Target dateTitle
07-Dec-2012Business Analysis Review
16-Jan-2013Business Case Review
31-Jan-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
88.5 days
Activity this month
6.2 days
Activity this year
15.5 days
Activity to date
16.0 days
Estimate to complete current year
61.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Alternative Search Engine Investigation
Code
UWS005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Craig Middlemass
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
08-May-2013