Report for February 2024

Report Date
February 2024

Achievements

  • VLE004: Final analysis of training data completed;
  • VLE004: Project closure documentation approved and project closed;
  • VLE004: Project trainer secondment completed at the end of February.

Issues

  • No issues due to closure of the project.

Next Steps

  • VLE004: No further steps required.  Project closed - February 2024.
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
Project closed - 28th February 2024. Project Closure document approved and linked to VLE004.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Learn Ultra: Training and Support
Code
VLE004
Programme
VLE Excellence
Management Office
ISG PMO
Project Manager
Lee-Ann Simpson
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
04-Apr-2022
Planning Date
04-Feb-2022
Delivery Date
31-Jan-2024
Close Date
28-Feb-2024
Overall Priority
Normal

Documentation