Report for July 2021

Report Date
July 2021

Overview

A way forward has been identified re the IoT infrastructure requirements to be provided by EIDF, as well as temporary and permanent elements to be provided by ISG.

We are remain in planning mode, although some prototyping, design and testing work has been carried out in parallel.   Technical architecture discussions with the EIDF team have informed our planning decisions and the project brief is underway.

RAG status.

Although there has been a delay, taken in the context of the significant impact from Covid-19 on DDI the UoE, and the CRD schools that will be the first users of the new version of the service, any delay to this project will be minor and not a cause for concern in itself.

Next steps:

Complete the project brief, technical designs, and plan.

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT Research & Innovation Service Phase 2
Code
WCD001
Programme
EIDF IoT Programme (EID)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Simon Chapple
Current Stage
Close
Status
Withdrawn
Project Classification
Transform
Start Date
11-Sep-2019
Planning Date
30-Jul-2021
Delivery Date
17-Dec-2021
Close Date
31-Jan-2022
Overall Priority
Highest
Category
Discretionary

Documentation