The project aims to:

1. Reduce time &resource to deploy new releases of uPortal software to live environment, by establishing a continuous integration and deployment environment for MyEd builds:

·         New releases of uPortal software can be easily merged with local customisations

·         Automated build and testing are applied to merged code

·         Including testing of integrations with test instances of co-dependent services

·         Automated deployment through the various staging environments to live

 

2. Apply this solution to upgrading MyEd on a more frequent basis, staying in line with most recent “solid” release of uPortal

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2015 BLUE 145.0 days 144.0 days 0.0