Responsive MyEd and EdWeb Integration - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2017 GREEN 475.0 days 531.2 days 1.0
Content
Status
Closed
Current Stage
Close
Start Date
Wednesday, 7 October 2015
Close Date
Friday, 27 October 2017
Project information
Project Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Session
17/18
16/17
15/16
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Project Category
Compliance
Overall Priority
Highest