Project journal

Title Description Author Post date
MyEd Upgrade completed

Phase 2 of the project to MyEd Upgrade project was deployed to LIVE on Tuesday 19th July 2017. This phase has deployed the upgraded version of UPortal v4.3 and incorporated developments to include  responsive MyEd using mobile devices and has been integrated to enhance styling with EdWeb.

Further deployments completed to rollout upgrade completed on 9th Aug and 17th Aug.  

All 3 deployments to LIVE were implemented without any downtime.

Karen Stirling 18-Aug-2017
New hardware deployment successfully completed

Phase one of the project to MyEd Upgrade project was seamlessly deployed to LIVE on Tuesday 19th July 2016. This phase has deployed new hardware for DEV TEST and LIVE environments, ensuring that the service has more than adequate capacity for the start of term.  

The deployment on LIVE was implemented without any downtime. 

Tim Gray 22-Jul-2016
MyEd Upgrade planning complete

IS Applications have finished planning a new project to upgrade the MyEd portal.

The project will be delivered in two phases. Phase 1 will upgrade the hardware infrastructure on DEV, TEST and LIVE. Phase 2 will upgrade the uPortal software introducing a new responsive theme to improve the user experience. It is expected that the updated MyEd will allow users to access their content much more easily on mobile devices.

Tim Gray 01-Mar-2016

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance