November Report
- Report Date
- November 2016
Achievements this period
- Phase 2: Dev Upgrade completed
- Angular development completed
- Announcements completed and ready to deploy to BETA and Dev
- All open JIRAs reviewed
- Work commenced on Office 365 Email Portlet
- Investigation work relating to Groups ongoing
Issues
- A decision on how groups will be managed has been agreed following discussions with Unicon to use PAGs, developers are currently investigating and testing this
- Decision agreed by Project team including Project Sponsor and Project Manager to revise milestones and move UAT into January with a late February deployment, this has been communicated out to the channel owners.
- Review of any impacts, dependencies between WEB009 and COM032 relating to the Calendar this has delaying commencement of java portlet work, now underway 7th Dec
- Discussion around possible additional work associated with web proxy work which may required additional funding.
Next Steps
- Complete Groups work
- Complete Calendar Portlet
- Complete TEST upgrade
- Prep work for UAT
The project status is currently GREEN
06-Dec-2016 | Phase 2 DEV Build Review | Build |
13-Dec-2016 | Phase 2 Integration Review | Integrate |
07-Feb-2017 | Phase 2 Acceptance Review | Accept |
21-Feb-2017 | Phase 2 Deployment | Deliver |
07-Mar-2017 | Phase 2 Deployment Review | Deliver |
21-Mar-2017 | Phase 3 Improved alignment between MyEd and EdWeb | Deliver |
04-Apr-2017 | Closure | Close |
- Approved budget
- 325.0 days
- Activity this month
- 40.5 days
- Activity this year
- 122.0 days
- Activity to date
- 263.0 days
- Estimate to complete current year
- 63.5 days
- Estimate to complete future years
- 0.0 days