November Report

Report Date
November 2016

Achievements this period

  • Phase 2: Dev Upgrade completed
  • Angular development completed
  • Announcements completed and ready to deploy to BETA and Dev
  • All open JIRAs reviewed
  • Work commenced on Office 365 Email Portlet
  • Investigation work relating to Groups ongoing

Issues

  • A decision on how groups will be managed has been agreed following discussions with Unicon to use PAGs, developers are currently investigating and testing this
  • Decision agreed by Project team including Project Sponsor and Project Manager to revise milestones and move UAT into January with a late February deployment, this has been communicated out to the channel owners.
  • Review of any impacts, dependencies between WEB009 and COM032 relating to the Calendar this has delaying commencement of java portlet work, now underway 7th Dec
  • Discussion around possible additional work associated with web proxy work which may required additional funding.

Next Steps

  • Complete Groups work
  • Complete Calendar Portlet
  • Complete TEST upgrade
  • Prep work for UAT

The project status is currently GREEN

06-Dec-2016 Phase 2 DEV Build Review Build
13-Dec-2016 Phase 2 Integration Review Integrate
07-Feb-2017 Phase 2 Acceptance Review Accept
21-Feb-2017 Phase 2 Deployment Deliver
07-Mar-2017 Phase 2 Deployment Review Deliver
21-Mar-2017 Phase 3 Improved alignment between MyEd and EdWeb Deliver
04-Apr-2017 Closure Close

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
325.0 days
Activity this month
40.5 days
Activity this year
122.0 days
Activity to date
263.0 days
Estimate to complete current year
63.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance