Report for July 2017

Report Date
July 2017

Achievements this period

  • Resolution of JIRAs impacted by upgrade - fixed and tested, including involvement from IS Helpline and key resource
  • Email portlet issue being investigated
  • Implementation plan updated with additional rollout tasks required
  • Re-deployment activity completed on 19th July to Group A servers, upgrade now available to MyEd Users
  • SVN to GIT documentation underway

Issues

  • Due to performance spikes the project team agreed to delay rollout to Group B Servers until key Development Technology resource back from annual leave this is planned for 10th August
  • Revised milestones to be confirmed for Deployment Review and Closure
  • Project has been highlighted to the IT Readiness project
  • Project budget has reviewed / agreed by DTI Senior Supplier notified to CIO of change of budget.

Next Steps

  • Resolution/ Closure of remaining  JIRAs
  • Re-deployment activity to complete for Group B Servers on 10th Aug
  • Portlet deployment for Library and Staff Details
  • Handover to support
  • Deployment review sign off
  • Closure

The project status is currently AMBER due to completing group B Servers upgrade activity and delay to sign off Deployment Review and Closure milestones which are being rescheduled

 

24-Aug-2017 (TBC) Phase 2 Deployment Review
31-Aug-2017 (TBC) Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE :
Change Status
Activity
Approved budget
375.0 days

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance