Mid August 2017
- Report Date
- August 2017
Achievements this period
- Email portlet issue being fixed however have put place an interim solution to O365 - IS Helpline are aware of this intermediate state
- Post -live Implementation plan updated with additional rollout tasks required
- Resolution of remaining JIRAs
- Re-deployment activity to complete for Group B Servers successfully deployed on 10th Aug
- Portlet deployment for Library, Survey, Optin/OptOut and Staff Details completed successfully on 17th Aug
- Handover to support completed
- SVN to GIT documentation completed
- Review of outstanding JIRAS to be estimated for a future small enhancements project
Issues
- Revised milestones to be confirmed for Deployment Review and Closure
- Key remaining JIRAS to be fixed and deployed are Email and chost - date to be arranged and agreement from Special CAB
Next Steps
- Deployment review sign off
- Closure
The project status is currently GREEN
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days