Report for May 2016

Report Date
May 2016

Achievements this period

  • TAD/Design Review completed
  • DEV build almost complete
  •  

Issues

  • Newer version of uPortal to be reinstalled on BETA, this has delayed progress on BETA
  • Continued overrun on other project work (mainly UWP for Mairi and DevOps for Peter) has impacted on developer's availability

Next Steps

  • Sign Off Dev
  • Start TEST build with puppet
  • Integration testing and load testing on TEST

Milestones

 

26-Feb-2016 Planning Review
10-Jun-2016 Phase 1: DEV Build Review
16-Jun-2016 Phase 1: Integration Review
06-Jul-2016 Phase 2 BETA Build Review
14-Jul-2016 Phase 1 Acceptance Review
28-Jul-2016 Phase 1 Deploy to LIVE
11-Aug-2016 Phase 2 DEV Build Review
12-Aug-2016 Phase 1 Deployment Review
19-Sep-2016 Phase 2 Integration Review
24-Oct-2016 Phase 2 Acceptance Review
08-Nov-2016 Phase 2 Deployment
30-Nov-2016 Phase 2 Deployment Review
15-Feb-2017 Phase 3 Improved alignment between MyEd and EdWeb
01-Mar-2017 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
325.0 days
Activity this month
25.0 days
Activity this year
93.0 days
Activity to date
93.0 days
Estimate to complete current year
87.0 days
Estimate to complete future years
150.0 days

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance