Report for July 2016

Report Date
July 2016

Achievements this period

  • Phase 1: Integration testing completed
  • Phase 1: UAT completed
  • Phase 1: LIVE build completed
  • Phase 1: Successfully deployed to LIVE
  • Phase 2: Milestones re-planned
  • Unicon Consultant days booked

Issues

  • No current issues to report

Next Steps

  • Complete BETA build
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
325.0 days
Activity this month
20.0 days
Activity this year
147.0 days
Activity to date
147.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
150.0 days

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance