Report for July 2016
- Report Date
- July 2016
Achievements this period
- Phase 1: Integration testing completed
- Phase 1: UAT completed
- Phase 1: LIVE build completed
- Phase 1: Successfully deployed to LIVE
- Phase 2: Milestones re-planned
- Unicon Consultant days booked
Issues
- No current issues to report
Next Steps
- Complete BETA build
- Approved budget
- 325.0 days
- Activity this month
- 20.0 days
- Activity this year
- 147.0 days
- Activity to date
- 147.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 150.0 days