Report for August 2016

Report Date
August 2016

Achievements this period

  • Phase 2: Work on BETA continues
  • All "BETABLOCKER" JIRAs assigned and progressed
  • Some JIRA's passed over to Unicon

Issues

  • Since the new infrastructure has been in place the service has encountered small but as yet unexplained outages. Production ahve contacted Unicon to assist.
  • The work to complete BETA is taking longer than expected, however the project team continue to strive for BETA sign off in early September

Next Steps

  • Resolve all JIRA for BETA
  • Complete BETA 
  • Start work on DEV
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
325.0 days
Activity this month
23.0 days
Activity this year
23.0 days
Activity to date
170.0 days
Estimate to complete current year
125.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Responsive MyEd and EdWeb Integration
Code
WEB009
Programme
Digital Transformation - User Centred Portal and Notifications
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Martin Morrey
Current Stage
Close
Status
Closed
Start Date
07-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Highest
Category
Compliance