Report for August 2016
- Report Date
- August 2016
Achievements this period
- Phase 2: Work on BETA continues
- All "BETABLOCKER" JIRAs assigned and progressed
- Some JIRA's passed over to Unicon
Issues
- Since the new infrastructure has been in place the service has encountered small but as yet unexplained outages. Production ahve contacted Unicon to assist.
- The work to complete BETA is taking longer than expected, however the project team continue to strive for BETA sign off in early September
Next Steps
- Resolve all JIRA for BETA
- Complete BETA
- Start work on DEV
- Approved budget
- 325.0 days
- Activity this month
- 23.0 days
- Activity this year
- 23.0 days
- Activity to date
- 170.0 days
- Estimate to complete current year
- 125.0 days
- Estimate to complete future years
- 0.0 days