November 2020
- Report Date
- November 2020
Achievements in Last Period
- Revised SOW with new Scrum training supplier and chose training dates
- Agreed approach for incorporating basic Agile tenets in Design System project
- Drafted portfolio management process diagram
- Continued analysis of project intake forms and procedures
- Worked with Service Management to set up a new WAC project template in Jira
Issues
- Long delays with Scrum training supplier have affected our abillity to address certain process improvements; we have engaged a different supplier
Next StepsĀ
- Finalise SOW with new Scrum training supplier
- Get team feedback on proposed portfolio management process
- Continue audit of WAC's Unidesk procedures and user help content
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days