December 2020
- Report Date
- December 2020
Achievements in Last Period
- Signed SOW with new Scrum training supplier
- Sent draft portfolio management process to WAC management
- Created Jira projects for WAC product backlogs (website and portal services)
Issues
- No issues to report
Next StepsĀ
- Work with supplier to customise Scrum training (in progress)
- Conduct Scrum training for WAC team on 19-20 January and determine next steps
- Get team feedback on proposed portfolio management process and determine next steps
- Continue audit of WAC's Unidesk procedures and user help content
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days