March 2020
- Report Date
- March 2020
Achievements in Last Period
- Completed remaining discovery sessions with WAC teams around internal processes
- Held initial session with WAC management team to begin discussing long-term vision
- Spoke with Sonia Virdi and Duncan Stephen about using Service Design methodology for this project
- Analysed project request and evaluation processes in use across WAC
- Researched potential suppliers of Scrum training
- Continued work on stakeholder analysis and comms plan for this and closely related projects
- Separated out the Design System as an independent project
Issues
- No issues to report
Next StepsĀ
- Create proposal for streamlining project intake processes across WAC
- Begin experimenting with new ways of working
- Create ITQ for Scrum training
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days