July 2020

Report Date
July 2020

Achievements in Last Period

  • Conducted Scrum pilot for the Short Online Courses website, including retrospective
  • Continued discussion with WAC managers about the strategic approach to this initiative
  • Evaluated Trello as a task tracking tool
  • Continued work on comms plan for this and closely related projects

Issues

  • Postponed Scrum training due to supplier availability issues

Next StepsĀ 

  • Finalise Scrum training syllabus and schedule new training dates
  • Write user stories for intake process pain points and prioritise
  • Evaluate Jira as a task tracking tool
  • Hold further discussion with WAC managers about future WAC service offering
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Future WAC Services
Code
WPS003
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Sheri Harrison
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
11-Feb-2020
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jan-2021
Overall Priority
Normal

Documentation