August 2020
- Report Date
- August 2020
Achievements in Last Period
- Wrote user stories for intake process pain points and set up a Jira project
- Began streamlining Unidesk queues
- Spoke further with Scrum training supplier about customising our course
- Scheduled strategy session with WAC managers about future WAC service offering
- Continued work on comms plan for this and closely related projects
Issues
- Scrum training dates still not agreed, due to supplier availability issues
Next StepsĀ
- Schedule new Scrum training dates and finalise syllabus
- Prioritise additional intake process improvements
- Hold strategy session with WAC managers about future WAC service offering
- Begin evaluating Jira as a task tracking tool
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days