August 2020

Report Date
August 2020

Achievements in Last Period

  • Wrote user stories for intake process pain points and set up a Jira project
  • Began streamlining Unidesk queues
  • Spoke further with Scrum training supplier about customising our course
  • Scheduled strategy session with WAC managers about future WAC service offering
  • Continued work on comms plan for this and closely related projects

Issues

  • Scrum training dates still not agreed, due to supplier availability issues

Next StepsĀ 

  • Schedule new Scrum training dates and finalise syllabus
  • Prioritise additional intake process improvements
  • Hold strategy session with WAC managers about future WAC service offering
  • Begin evaluating Jira as a task tracking tool
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Future WAC Services
Code
WPS003
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Sheri Harrison
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
11-Feb-2020
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Jan-2021
Overall Priority
Normal