Report for January 2021

Report Date
January 2021

Achievements this period

  • Deployment issues noted in December have been resolved and the update deployed to LIVE
  • Deployment sign off review achieved

Issues

  • None

Next Steps

  • Project closure circulated to the project team
  • Project closure achieved at WIS

Milestones

Deployment Sign Off 15-Jan-2021
Closure 22-Jan-2021
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
33.0 days
Activity this month
5.5 days
Activity this year
26.0 days
Activity to date
26.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual EdWeb Upgrade
Code
WPS005
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Bruce Darby
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
31-Aug-2020
Planning Date
n/a
Delivery Date
07-Dec-2020
Close Date
12-Feb-2021
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation