Report for May 2021

Report Date
May 2021

Achievements this period

  • React upgrade on DEV completed
  • uPortal upgrade on DEV has progressed well and is currently being tested before pushing onto TEST.

Issues

  • Milestone changes completed and approved by project team and WIS. This project will carryover into 2021/22 by 1 week to cover the DSOR and Closure period.

Next Steps

  • Complete the uPortal and JDK upgrade on DEV
  • React, uPortal and JDK upgrade to TEST complete
  • Integration testing complete for React, uPortal and JDK
  • UAT to commence

Milestones

uPortal upgrade DEV complete 31-May-2021
Open JDK Upgrade - DEV 04-Jun-2021
uPortal, React and JDK Integration Testing complete 18-Jun-2021
MyEd navigation fix from wps004 Deploy to LIVE 25-Jun-2021
uPortal, Open JDK and React UAT Complete 09-Jul-2021
Deploy to LIVE: uPortal and React 14-Jul-2021
Open JDK Deploy to LIVE 21-Jul-2021
Delivery for Notifications / User / Staff interface complete 21-Jul-2021
Deployment sign off review (React and uPortal / JDK) 04-Aug-2021
Closure 06-Aug-2021
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Time is amber as there was a carryover into 2021/22 to complete DSOR and Closure. There is still significant work to complete in 2020/21 (Integration, UAT and deployment) and although the project team is confident this can be achieved and resourcing is assigned, the risk remains that there could be additional carryover into 2021/22 to complete the project.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Milestone changes approved, and carryover of 1.5 days into 2021/22 to complete DSOR and Closure.
Activity
Approved budget
100.0 days
Activity this month
15.0 days
Activity this year
62.0 days
Activity to date
62.0 days
Estimate to complete current year
38.0 days
Estimate to complete future years
1.5 days

Project Info

Project
Annual Portal Services Upgrade
Code
WPS006
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
16-Oct-2020
Planning Date
22-Jan-2021
Delivery Date
29-Jul-2021
Close Date
05-Nov-2021
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation