Report for May 2021
- Report Date
- May 2021
Achievements this period
- React upgrade on DEV completed
- uPortal upgrade on DEV has progressed well and is currently being tested before pushing onto TEST.
Issues
- Milestone changes completed and approved by project team and WIS. This project will carryover into 2021/22 by 1 week to cover the DSOR and Closure period.
Next Steps
- Complete the uPortal and JDK upgrade on DEV
- React, uPortal and JDK upgrade to TEST complete
- Integration testing complete for React, uPortal and JDK
- UAT to commence
Milestones
uPortal upgrade DEV complete | 31-May-2021 |
Open JDK Upgrade - DEV | 04-Jun-2021 |
uPortal, React and JDK Integration Testing complete | 18-Jun-2021 |
MyEd navigation fix from wps004 Deploy to LIVE | 25-Jun-2021 |
uPortal, Open JDK and React UAT Complete | 09-Jul-2021 |
Deploy to LIVE: uPortal and React | 14-Jul-2021 |
Open JDK Deploy to LIVE | 21-Jul-2021 |
Delivery for Notifications / User / Staff interface complete | 21-Jul-2021 |
Deployment sign off review (React and uPortal / JDK) | 04-Aug-2021 |
Closure | 06-Aug-2021 |
- Approved budget
- 100.0 days
- Activity this month
- 15.0 days
- Activity this year
- 62.0 days
- Activity to date
- 62.0 days
- Estimate to complete current year
- 38.0 days
- Estimate to complete future years
- 1.5 days