Report for September 2021
- Report Date
- September 2021
Achievements in Last Period
-
Prototype design system store front built and deployed to the pantheon platform
-
Store front code base installed and controlled by a custom upstream profile
-
Figma education account opened to enable design components
-
Design system Information Architecture completed
Issues
-
No new issues last month
Next Steps
- Design content for GitLab
-
Design content for prototype storefront
-
Component inventory
-
Configuring Figma file to replicate the bootstrap elements
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days