Report for October 2021

Report Date
October 2021

Achievements in Last Period

  • Designed content for GitLab
  • Designed content for prototype storefront

  • Component inventory completed

  • Configured Figma file to replicate the bootstrap elements

Issues

  • No new issues last month

Next Steps 

  • Develop the navigation and menu pattern component
  • Agree/define branding information for DS components
  • Finalise icon suite decision and implementation steps
  • Complete the inclusive language guide
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project is on track and RAG status is GREEN.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023