Report for November 2021

Report Date
November 2021
Report Date
November 2021

Achievements in Last Period

  • Finalised icon suite decision (bootstrap)
  • Finalised 12-month product road map
  • Agreed core content fields for component pages
  • Finalised Storefront IA
  • Created first version of the contribution process/workflow.
  • Aligned communications with the Web Publishing Platform project (WPS008)

Issues

  • Waiting for senior management sign off to publish the Inclusive Language Guide

Next StepsĀ 

  • Release of new Design System storefront
  • Test the contribution process with the Web Publishing Platform product
  • Creation of self-assessment form for those who wish to contribute to the Design System
  • Publish the Inclusive Language Guide
  • Release Design System v0.1 with a core set of components and variants.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023
Overall Priority
Normal

Documentation