Design System December 2020

Report Date
December 2020

Achievements in Last Period

  • Decision on which platform to use (for hosting the DS content) has been completed
  • DS platform populated with portions of available content and demonstrated to stakeholders

Issues

  • Stakeholders have not yet fully defined all deliverables and so time and scope are amber

Next Steps 

  • Fully define (and implement more of) the outstanding deliverables in conjunction with stakeholders and project team 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
AMBER (time and scope) as stakeholders have not fully defined all deliverables.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023
Overall Priority
Normal

Documentation