Report for August 2022
- Report Date
- August 2022
Achievements in Last Period
-
Sprint 21 started – this is also an IP iteration (#4)
-
4th PI Planning session took place on 31st August
- Decision taken to restart sprints on 7th September (sprint 22) – this takes into account feedback from previous PI planning sessions and planned annual leave during August
- Work to complete the final stage of PI planning prior to recommencing sprints (on 7th Sep) is continuing – the Jira tickets will be created w/e 2nd Sep
- Editorial Working Group - inaugural meeting took place on 9th August
- Presentation of ILG to CAHSS took place 23rd Aug Presentation of ILG to MVM to be scheduled in Sep
- Planning of DS 0.2 Jira tickets has started based on the previous PI planning sessions
- Changes to Jira template reviewed with Scrum team
- Purpose of Scrum ceremonies reviewed with team in order to look for opportunities to improve and optimise use of team members’ time
- RFC Submission form drafted and uploaded to CAB Wiki page
Issues
- None
Next Steps
- Scrum Master handover (scheduled 6th Sep)
- Continue with Designathon next steps
- Start video documentation for desktop Search Summary component
- Analysis of Multibrand Checklist session to be completed and outputs reviewed by stakeholders attending the checklist session
- Inclusive data gathering to be added to Editorial Working Group backlog
- Start sprint 22
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days