Report for August 2022

Report Date
August 2022

Achievements in Last Period

  • Sprint 21 started – this is also an IP iteration (#4)

  • 4th PI Planning session took place on 31st August

  • Decision taken to restart sprints on 7th September (sprint 22) – this takes into account feedback from previous PI planning sessions and planned annual leave during August
  • Work to complete the final stage of PI planning prior to recommencing sprints (on 7th Sep) is continuing – the Jira tickets will be created w/e 2nd Sep
  • Editorial Working Group - inaugural meeting took place on 9th August
  • Presentation of ILG to CAHSS took place 23rd Aug Presentation of ILG to MVM to be scheduled in Sep
  • Planning of DS 0.2 Jira tickets has started based on the previous PI planning sessions
  • Changes to Jira template reviewed with Scrum team
  • Purpose of Scrum ceremonies reviewed with team in order to look for opportunities to improve and optimise use of team members’ time
  • RFC Submission form drafted and uploaded to CAB Wiki page

Issues

  • None

Next Steps 

  • Scrum Master handover (scheduled 6th Sep)
  • Continue with Designathon next steps
  • Start video documentation for desktop Search Summary component
  • Analysis of Multibrand Checklist session to be completed and outputs reviewed by stakeholders attending the checklist session
  • Inclusive data gathering to be added to Editorial Working Group backlog
  • Start sprint 22
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023
Overall Priority
Normal

Documentation