Report for October 2022

Report Date
October 2022

Achievements in Last Period

  • Completed sprint 23 and started sprint 24.
  • Review for new Jira template identified
  • Continue planning of next Designathon events.
  • Clarify of deliverables for next release (after sprint 25).
  • Kicked off liaison with the Degree Finder project to set expectations and create clear lines of communication to support it delivery over the next 3 years.
  • Kicked off the colour audit and identified options to ensure accessibility targets and standards are met.

Issues

  • Re-planning of strategic focus for future releases (after sprint 25) required to take place before the December holidays.

Next StepsĀ 

  • Plan Scrum Master training and accreditation.
  • Plan and run next Designathon events.
  • Finalise and publish EdGEL and Bootstrap update process.
  • Identify next Items for CAB.
  • Identify and agree clear direction and priorities for after sprint 25 (new calendar year).
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023
Overall Priority
Normal

Documentation