Report for March 2023
- Report Date
- March 2023
Achievements in Last Period
- EdGEL updates fully applied to Figma Design library
- Created draft report of Design System delivery for 6-12 months and future options.
Issues
- Limited resource to support continuous improvement.
Next StepsĀ
- Have high level discussions on future options.
- Plan project closure.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days