Design System February 2021

Report Date
February 2021

Achievements in Last Period

  • Completed planning documentation and stage
  • Completed Sprint 2 and produced DS workflow process

Issues

  • Some deliverables have not yet been fully defined and so time and scope are amber

Next Steps 

  • Complete specification of the undefined deliverables 
  • Complete the third sprint and produce the corresponding DS increment
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
AMBER (time and scope) as some deliverables have not yet been fully defined.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023
Overall Priority
Normal

Documentation