Design System April 2021

Report Date
April 2021

Achievements in Last Period

  • Completion (and agreement) of documented roles and responsibilities for all parts/processes of the Design System
  • Improved cross-functional team working and productivity through "norming" agile working practices, meetings and events
  • Progress developing more backlog deliverables and further definition of the remaining backlog items

Issues

  • Due to the month long delay in starting the WPP implementation project (caused by the protracted contract negotiations) there’s been a knock-on delay to the Design System project. The WPP implementation was due to start on 12th April but is now due to start on the 11th May. There are numerous ties between the WPP and DS projects, in that they inform each other, with the DS shaping the form of some WPP elements and the WPP elements dictating some of the DS content. Essentially the delay has meant that sprint 4, due to complete on 30th April, is now due to complete on 14th May. Also, looking further ahead, I believe we’ll need an additional sprint to bridge the delay and ensure we deliver the MVP. 

Next Steps 

  • Continuing iterative development of the Design System in next sprint
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
AMBER (on time) as a linked/dependency project (WPP) has been delayed by 1 month
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Design System
Code
WPS007
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Stratos Filalithis
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
10-Nov-2020
Planning Date
12-Feb-2021
Delivery Date
30-Jun-2022
Close Date
31-Jul-2023