Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2021 AMBER 0.0 days 0.0 days 0.0

Project Info

Project
Replace EdWeb Infrastructure
Code
WPS009
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Bruce Darby
Current Stage
Plan
Status
In Progress
Start Date
16-Apr-2021
Planning Date
07-May-2021
Delivery Date
18-Jun-2021
Close Date
09-Jul-2021
Overall Priority
Normal

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.