Impact

Priority and Funding

This project is classified as Normal priority. This is not expected to be modified, but it is important that the plan is adhered to so that the deployment window is met. The project was originally planned for 21/22 but has been brought forward into this financial year.

It is a core-funded project.

Impact and Dependencies

The upgrade of the OS on the servers included in this project will increase the Web team's confidence in the infrastructure, and it is important that the timings of the deployments in each environment around other EdWeb maintenance activities. There are, at the moment, no other dependencies within the WPS programme but the project team should be cognisant of other infrastructure projects and relatedmaintenance activity.

Lessons learned from previous projects

Initial discussions with the project team have indicated the high importance of timings for deployments, particularly in LIVE, so that any downtime is kept to a strict minimum. This is because of the high priority of the EdWeb service and the business need to maintain the highest level of availability.

 

Project Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner
1 Project resources may become conflicted GREEN GREEN Open Retain David Watters
2 The technical resolution required may become more more complex than currently envisaged GREEN GREEN Open Reduce Peter Jackson
3 Possible delays to delivery of VMs GREEN GREEN Open Reduce Martin Campbell
4 Delivery date in LIVE will need to be planned carefully GREEN GREEN Open Reduce Bruce Darby
5 Complexity of technical architecture may not be fully understood GREEN GREEN Open Reduce Peter Jackson
6 Web Publishing Team can feel 'excluded' GREEN GREEN Open Reduce Bruce Darby

Project Info

Project
Replace EdWeb Infrastructure
Code
WPS009
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bruce Darby
Current Stage
Close
Status
Closed
Start Date
16-Apr-2021
Planning Date
11-Jun-2021
Delivery Date
18-Aug-2021
Close Date
02-Sep-2021
Overall Priority
Normal

Documentation

Plan