Closure Report

 

Project Summary

Within the EdWeb infrastructure, the varnish and memcache servers had already reached their operating system (CentOS 6)  end of life. The move of the varnish servers to CentOS 7 was believed to be relatively straightforward, but the upgrade of the memcache servers required code changes and needed to be delivered as a project given the system's history of sensitivity to losing individual cache components. This project oversaw the necessary infrastructure upgrades to the varnish and memcache servers across the various environments.

Scope

The scope of this project included the following:

  • Review cache server infrastructure
  • Replace/update 18 memcache servers (2 x Dev, 4 x Test, 4 x Staging, 4 x Training, 4 x Live) in the EdWeb infrastructure  
  • Replace/update 16 memcache servers (4 x Test, 4 x Staging, 4 x Training, 4 x Live) in the EdWeb infrastructure
  • Review bamboo plans and deployment documentation 
  • Update TAD and build documentation 

Analysis of Resource Usage:

Staff Usage Estimate: 40 days

Staff Usage Actual: 30? days

Staff Usage Variance: -25%

Other Resource Estimate: n/a

Other Resource Actual: n/a

Other Resource Variance: n/a

 

Outcome

Objectives & Deliverables

 

Priority

Achieved?

O1 To upgrade the operating system (across all relevant environments)on the current memcache servers within the EdWeb infrastructure

 

 

D1. Upgraded memcache servers on the Dev, Test, Staging, Training and Live EWeb environments

Must Have

Yes
D2. Upgraded varnish servers on the Test, Staging, Training and Live EWeb environments Must Have Yes

 O2 To update all relevant technical and support documentation

   
D2. Updated architecture and an updated Technical Architecture Document (TAD) Must Have Yes
D3. Updated build documentation Must Have Yes
D4. An updated Bamboo plan Must Have Yes

D5. Updated deployment documentation

Must Have Yes

 

Explanation for Variance

  • Effort

There is some variance to report in terms of effort. A three point estimate carried out at the planning stage suggested a total, for Applications, of 40 days and the final figure is 30 days. The reason for the lower figure is simply that the estimates for the server builds proved to be on the 'generous' side and the development team did a great job in getting these built more efficiently than anticipated.

 

  • Time

There is little variance in this respect. The eventual go-live date was six days later than that originally planned but this was within the tolerance of the project and did not cause any problems for anyone involved. The closure report has been delayed by a few weeks because of sickness absence, something that cannot be avoided.

 

  • Scope

No major differences here either. The stated scope covered the replacement of the varnish and memcache servers across each of the environments, and that is what was achieved.

 

Key Learning Points

No explicit lessons learned were passed on.

Outstanding Issues

There are no reported issues.

 

Project Info

Project
Replace EdWeb Infrastructure
Code
WPS009
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bruce Darby
Current Stage
Close
Status
Closed
Start Date
16-Apr-2021
Planning Date
11-Jun-2021
Delivery Date
18-Aug-2021
Close Date
02-Sep-2021
Overall Priority
Normal

Documentation

Close