Report for June 2021
- Report Date
- June 2021
Achievements this period
- Completed project brief and planning
- Started architecture design for environments
- Ordered new servers
Issues
- Resourcing issues for subsequent stages because of availability
Next Steps
- Complete build of servers in DEV
- Plan build of remaining environments
- Pin down resources for work in other environments
Milestones
Stage | Milestone | Due Date |
---|---|---|
Build | Build review & sign-off | 30-Jul-2021 |
Integrate | Load testing sign-off | 10-Aug-2021 |
Deliver | Deployment in LIVE | 18-Aug-2021 |
Deliver | Deployment review and sign-off | 23-Aug-2021 |
Close | Project closure | 02-Sep-2021 |
RAG
- GREEN
- Approved budget
- 40.0 days
- Activity this month
- 6.0 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 19.7 days
- Estimate to complete future years
- 10.0 days