Report for July 2021
- Report Date
- July 2021
Achievements this period
- Build of new servers in DEV and other environments
- Started migration to new servers in DEV
- Migration of remaining environments scheduled
- Load testing planned
Issues
- None reported
Next Steps
- Finalise migration to new servers in DEV
- Complete migration of remaining environments
- Finish load testing
- Migration to new servers in LIVE
Milestones
Build | Build review & sign-off | 06-Aug-2021 |
Integrate | Load testing sign-off | 13-Aug-2021 |
Deliver | Deployment in LIVE | 24-Aug-2021 |
Deliver | Deployment review and sign-off | 31-Aug-2021 |
Close | Project closure | 09-Sep-2021 |
RAG
- GREEN
- Approved budget
- 40.0 days
- Activity this month
- 9.0 days
- Activity this year
- 16.0 days
- Activity to date
- 16.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 21.0 days