Report for July 2021

Report Date
July 2021

Achievements this period

  • Build of new servers in DEV and other environments
  • Started migration to new servers in DEV
  • Migration of remaining environments scheduled
  • Load testing planned

Issues

  • None reported

Next Steps

  • Finalise migration to new servers in DEV
  • Complete migration of remaining environments
  • Finish load testing
  • Migration to new servers in LIVE

Milestones

Build Build review & sign-off 06-Aug-2021
Integrate Load testing sign-off 13-Aug-2021
Deliver Deployment in LIVE 24-Aug-2021
Deliver Deployment review and sign-off 31-Aug-2021
Close Project closure 09-Sep-2021

 

 

RAG

  • GREEN
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
9.0 days
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
21.0 days

Project Info

Project
Replace EdWeb Infrastructure
Code
WPS009
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bruce Darby
Current Stage
Close
Status
Closed
Start Date
16-Apr-2021
Planning Date
11-Jun-2021
Delivery Date
18-Aug-2021
Close Date
02-Sep-2021
Overall Priority
Normal

Documentation