Report for August 2021
- Report Date
- August 2021
Achievements this period
- All pre-production environments signed off
- UAT signed off
- Load testing signed off
- Deployment to LIVE completed
Issues
- None reported
Next Steps
- Deployment review
- Project closure
Milestones
Build | Build review & sign-off | 06-Aug-2021 |
Integrate | Load testing sign-off | 13-Aug-2021 |
Deliver | Deployment in LIVE | 24-Aug-2021 |
Deliver | Deployment review and sign-off | 31-Aug-2021 |
Close | Project closure | 09-Sep-2021 |
RAG
- GREEN
- Approved budget
- 40.0 days
- Activity this month
- 12.0 days
- Activity this year
- 12.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 10.0 days
- Estimate to complete future years
- 0.0 days