Report for August 2021

Report Date
August 2021

Achievements this period

  • All pre-production environments signed off
  • UAT signed off
  • Load testing signed off
  • Deployment to LIVE completed

Issues

  • None reported

Next Steps

  • Deployment review
  • Project closure

Milestones

Build Build review & sign-off 06-Aug-2021
Integrate Load testing sign-off 13-Aug-2021
Deliver Deployment in LIVE 24-Aug-2021
Deliver Deployment review and sign-off 31-Aug-2021
Close Project closure 09-Sep-2021

 

 

RAG

  • GREEN
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
12.0 days
Activity this year
12.0 days
Activity to date
28.0 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Replace EdWeb Infrastructure
Code
WPS009
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bruce Darby
Current Stage
Close
Status
Closed
Start Date
16-Apr-2021
Planning Date
11-Jun-2021
Delivery Date
18-Aug-2021
Close Date
02-Sep-2021
Overall Priority
Normal

Documentation