Impact
Priority and Funding
This is a core funded, normal priority, compliance project.
Impact and Dependencies
There is a dependency with the general on-going MyEd upgrades and work.
Deliverable 6.8 - JIRA 102: Assess effort required to implement design system on MyEd: There is a dependency on the design work being sufficiently advanced in order for the design assessment to be carried out to see if it can be implemented on MyEd. The design work is being completed separately from WPS012, the assessment will be carried out in WPS012.
Lessons learned from previous projects
The project will complete the assessments first and include a milestone for the project team to signoff. This will ensure that development work is agreed and estimated before starting.