Impact

Priority and Funding

This is a core funded, normal priority, compliance project.

 

Impact and Dependencies

There is a dependency with the general on-going MyEd upgrades and work.

Deliverable 6.8 - JIRA 102: Assess effort required to implement design system on MyEd: There is a dependency on the design work being sufficiently advanced in order for the design assessment to be carried out to see if it can be implemented on MyEd. The design work is being completed separately from WPS012, the assessment will be carried out in WPS012.

Lessons learned from previous projects

The project will complete the assessments first and include a milestone for the project team to signoff. This will ensure that development work is agreed and estimated before starting.

 

Project Risks

Risk that DevTech resources are not available GREEN Retain Mark Lang
Risk that SW Dev resources are not available GREEN Retain John Allison
Risk that WAC/LTW resources are not available GREEN Retain Stratos Filalithis
Risk that software development items may use more budget than anticipated GREEN Retain Stratos Filalithis
Risk that deliverable 6.8 assessment is not able to progress GREEN Reduce Mary Elder

Project Info

Project
Annual Portal Services Upgrade
Code
WPS012
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
25-Nov-2021
Planning Date
23-Dec-2021
Delivery Date
06-Oct-2022
Close Date
22-Nov-2022
Overall Priority
Normal