Report for June 2022

Report Date
June 2022

Achievements this period

  • uPortal and JDK TEST upgrade completed
  • UAT completed on uPortal amd JDK TEST
  • Milestone re-plans completed for next financial year

Issues

  • None

Next steps

  • uPortal and JDK Deployment upgrade to be completed on 06/07/2022
  • Analysis for Google Analytics 4 to be completed in July
  • Google Analytics 4 to be deployed to DEV in July

Milestones

uPortal and JDK Deploy to LIVE 06-Jul-2022
Assessment for Google Analytics 13-Jul-2022
Google Analytics 4 implemented on MyEd Dev 22-Jul-2022
Google Analytics 4 implemented on MyEd TEST 24-Aug-2022
React upgrade - DEV complete 06-Sep-2022
React TEST upgrade: integration complete 14-Sep-2022

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Milestone and budget change - Issue 5. The project is carrying over into 2022/23 to complete the Google Analytics 4 and React upgrades
Activity
Approved budget
121.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
23.0 days

Project Info

Project
Annual Portal Services Upgrade
Code
WPS012
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
25-Nov-2021
Planning Date
23-Dec-2021
Delivery Date
06-Oct-2022
Close Date
22-Nov-2022
Overall Priority
Normal

Documentation