Report for July 2022

Report Date
July 2022

Achievements this period

  • uPortal and JDK Deployments completed on 06/07/2022
  • Replan and resourcing assigned for next financial year 

Issues

  • Developer annual leave, their ADR and work on P&M has meant that the Google Analytics analysis and deployment to DEV will be pushed into the next financial year
  • Annual leave of developer and Service Owner means no progress will be made until mid August

Next steps

  • Analysis for Google Analytics 4 to be completed
  • Google Analytics 4 to be deployed to DEV and TEST
  • React upgrade to DEV to commence in September

Milestones

Assessment for Google Analytics 18-Aug-2022
Google Analytics 4 implemented on MyEd Dev 26-Aug-2022
Google Analytics 4 implemented on MyEd TEST 31-Aug-2022
React upgrade - DEV complete 06-Sep-2022
React TEST upgrade: integration complete 14-Sep-2022
React - UAT Complete 30-Sep-2022
React Upgrade to LIVE 06-Oct-2022
Google Analytics 4 implemented on MyEd LIVE 12-Oct-2022
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
121.0 days
Activity this month
9.7 days
Activity this year
103.0 days
Activity to date
1.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
26.0 days

Project Info

Project
Annual Portal Services Upgrade
Code
WPS012
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
25-Nov-2021
Planning Date
23-Dec-2021
Delivery Date
06-Oct-2022
Close Date
22-Nov-2022
Overall Priority
Normal

Documentation