Report for November 2024

Report Date
November 2024

Achievements for Last Period

  • Project Planning complete

Issues

  • None to report

Next Steps

  • Complete the Analysis of Data Retention Policies
  • Complete the BRD

The project status is GREEN.

Project Milestones

Stage Milestone Due Date Complete
Plan Planning & Foundations Sign Off - Major 27-Nov-2024 Yes
Execute Release 1 Complete 28-Feb-2025 No
Execute Release 2 Complete 09-May-2025 No
Execute Release 3 Complete 18-Jul-2025 No
Close Close - Major 25-Jul-2025 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
250.0 days
Activity this month
10.5 days
Activity this year
11.5 days
Activity to date
11.5 days
Estimate to complete current year
234.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Portal Service Upgrade 24/25
Code
WPS020
Programme
ISG - Web and Portal Services Programme (WPS)
Management Office
ISG PMO
Project Manager
Anna Forostianko
Project Sponsor
Stratos Filalithis
Current Stage
Execute
Status
In Progress
Start Date
14-Oct-2024
Planning Date
21-Nov-2024
Delivery Date
18-Jul-2025
Close Date
25-Jul-2025
Overall Priority
Normal

Documentation