Report for November 2024
- Report Date
- November 2024
Achievements for Last Period
-
Project Planning complete
Issues
- None to report
Next Steps
- Complete the Analysis of Data Retention Policies
- Complete the BRD
The project status is GREEN.
Project Milestones
Stage | Milestone | Due Date | Complete |
---|---|---|---|
Plan | Planning & Foundations Sign Off - Major | 27-Nov-2024 | Yes |
Execute | Release 1 Complete | 28-Feb-2025 | No |
Execute | Release 2 Complete | 09-May-2025 | No |
Execute | Release 3 Complete | 18-Jul-2025 | No |
Close | Close - Major | 25-Jul-2025 | No |
- Approved budget
- 250.0 days
- Activity this month
- 10.5 days
- Activity this year
- 11.5 days
- Activity to date
- 11.5 days
- Estimate to complete current year
- 234.9 days
- Estimate to complete future years
- 0.0 days